Click here to view presentation
Interior Renovations
- Bell Elementary - under contract
- Burroughs Elementary - under contract
- Hawthorne Elementary - complete
- Sequoyah Elementary - summer 2025
- Skelly Elementary - complete
- Thoreau Demonstration Academy - summer 2025
- Wayman Tisdale Fine Arts Academy - summer 2024
- Eugene Field Elementary (partial) - complete
Accessibility, ADA Improvements
- East Central High School - restrooms complete
- Edison Preparatory - complete
- Hale High School - in progress
- Elevator upgrades at Sequoyah, Webster, Thoreau - under contract
- Parking lot resurfacing at Anderson, Bell, Patrick Henry, Hawthorne, Skelly, East Central High School, Edison Preparatory, Education Service Center - phase 1 complete
- LED lighting upgrades - complete
- Sidewalk improvements - ongoing
Roofing
- Disney Elementary - complete
- Edison Preparatory - complete
- Eisenhower International School - under contract
- Eliot Elementary - complete
- Greenwood Leadership Academy - complete
- Lanier Elementary - complete
- MacArthur Elementary - complete
- Peary Elementary - complete
- Skelly Elementary - complete
- Street School - complete
- Webster Fieldhouse - in progress
Enhanced Secure Entries
- All elementary schools now have double entry systems
- Summer entry projects will include:
- Central Middle and High School
- Hale High School
- Memorial Middle School
- East Central High School
- Webster Middle and High School
- Tulsa MET
- Phoenix Rising
- North Star Academy
- Memorial Middle School
Dining and Kitchen Improvements
- Edison Preparatory - complete
- Memorial High School - under contract
- Rogers Middle and High School - under contract
- Eliot Elementary - under contract
- John Hope Franklin Elementary - nearly complete
- Walk-in freezer coolers at Hawthorne Skelly Upper, John Hope Franklin - complete
Technology Network Systems and Security Upgrades
- District phone system replacement - complete
- Intercom systems replacements - June 2023
- Radio system upgrade - in progress
- Lightning prediction system - complete
- Security system upgrade - nearly complete
- Marquees - nearly complete
Playgrounds
- Bell Elementary - under contract
- Carnegie Elementary - under contract
- Council Oak Elementary - complete
- Cooper Elementary - under contract
- Eugene Field Elementary - under contract
- Hawthorne Elementary - complete
- John Hope Franklin Elementary - complete
- Kendall-Whittier Elementary - three complete
- Kerr Elementary - complete
- McKinley Elementary - complete
- Project Accept - complete
- Robertson Elementary - under contract
- Skelly Elementary - complete
- Salk Elementary - under contract
Athletics
- Booker T. Washington High School tennis courts - complete
- Booker T. Washington High School stadium waterproofing/refresh - complete
- East Central High School - scoreboard/time clock replacement - under contract
- East Central High School fieldhouse and YMCA collaboration - complete
- Edison Preparatory fieldhouse sound system - complete
- Hale High School turf replacement - complete
- Memorial High School scoreboard/time clock replacement - under contract
- Rogers Middle and High School turf replacement - complete
- Rogers Middle and High School fieldhouse sound system - complete
- Rogers Middle and High School visitors bleachers and restrooms - under contract
- Webster Middle and High School fieldhouse sound system - complete
- Helmets - phase 1 complete
- Physical education equipment funds for all schools - complete
Quality Learning Materials and Programs
Includes 10 major categories including all curricular areas and programs. Many expenditures are routine and ongoing.
- New sound control boards at Booker T. Washington High School, East Central Middle School, Monroe Demonstration Academy, and Lewis in Clark Elementary - complete
- New sound control board at Skelly - in progress
- New band uniforms for all high schools - East Central, Hale and Webster complete
- Webster band room addition - in progress
Library Digital and Print Resources
- Library books and materials budgets released to all schools - complete
- Technology equipment upgrades budgets released to all schools - complete
- Subscriptions to online renewals for all sites - complete for 22/23
- School library improvements
- Key Elementary refresh - complete
- Kendall-Whittier Elementary refresh - nearly complete
- Central Middle and High School - in progress
- Webster Middle and High School - in progress
Other
- New lab materials have been purchased for science labs across all secondary sites to refresh needs, aligned with grade level and hands on lab experiences.
- Greenwood Rising Museum - iPads purchased and class visits have started
- Early Childhood Education Expansion - Skelly Primary and Hawthorne modifications complete
- Program Expansion
- Grissom Montessori resources and building modifications: phase I complete
- Grissom Phase ll: Add classroom sinks in design for summer 2023
- Eugene Field Montessori resources and modifications - complete
- Eugene Field trailer removal and replacement with adjacent property in progress